Consultants call long rifle-range–Daee connection infeasible; committee refocuses trail plan on nearer AB Mountain zones

Skagway Parks & Recreation Committee · October 8, 2025

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trail consultants told the Parks & Recreation Committee that a continuous rifle-range–Daee multiuse connection would be technically difficult and costly; the committee voted to refocus the study on zones 3 and 4 of AB Mountain and to include multiuse concepts suitable for grant funding.

Trail consultants Respec and subcontractors told the Skagway Parks & Recreation Committee on Oct. 8 that the long-distance trail connecting the rifle range to the Daee boat launch was constrained by cliffs, boulder fields and drainage—including a waterfall and Mathews Creek—and would be cost‑prohibitive to build and maintain as originally envisioned.

Consultant Eddie, of Tarming and Trails, said field scouting showed “very technically demanding constraints” and that a multiuse ATV/horse/bicycle connection would likely require blasting, heavy mobilization and possibly helicopter lifts. He warned that some ATV-grade options could cost roughly $320,000–$330,000 per mile in the worst terrain. “It’s a really cool idea. It’s just really not feasible as something the town hasn’t agreed to maintain or fund long term,” he said.

Given the terrain and long‑term maintenance liabilities—consultants cited a rule of thumb that annual maintenance can approach 10% of construction cost—the committee voted to redirect the project team to focus on zones 3 and 4 of the AB Mountain area (the Nakube West / Yacotania Point corridor) and to develop a multiuse concept plan that would be more competitive for grants and easier for the municipality to sustain.

Motion and vote: Committee member Ryan Hansen moved to refocus the rifle-range‑to‑Daee concept on zones 3 and 4 and to include multiuse elements; Chair Spencer Morgan seconded and the motion carried by voice assent. Staff and consultants will rewrite the scope to produce a high‑level concept plan using existing lidar/topography that can be used for grant applications and more detailed field verification.

Why it matters: consultants said the original scope would require substantial capital outlay and recurring maintenance, could strain emergency services, and would trigger more extensive permitting (wetland/SHPO/environmental reviews) where Mathews Creek and other fish-bearing drainages are crossed. Instead, the consultants recommended developing a variety of shorter, fundable experiences—gravel universal access sections, hike/bike loops and improved trailheads near town—both to spread use across the landscape and to increase the chances of funding approval.

Next steps: staff will ask the consultants to prepare a concept plan for zones 3 and 4 suitable for pursuing state and federal grant funding; the committee asked that the budget and scope reflect realistic construction and 10% annual maintenance assumptions.