Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Council awards Allied Building Services contract to repair DPW wall, add gate and tuckpointing
Summary
After discussing structural unknowns, the council approved a contract with Allied Building Services to remove and rebuild sections of a failing DPW wall, install a 24-foot gate and tuckpoint roughly 2,200–2,400 feet of wall; staff included a substantial contingency to cover unforeseen deterioration.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Berkeley City Council approved a contract on March 2 to repair sections of a 75-year-old Department of Public Works brick wall, install a new gate and perform extensive tuckpointing.
Facilities manager Alex Brown outlined the work: remove approximately 120 feet of wall on the Phillips side, rebuild about 75 feet, install a roughly 40-foot gate and approach, and tuckpoint roughly 2,200–2,400 feet of existing brick wall. Brown said the work is intended to address a safety hazard, provide an additional DPW yard access point while Bacon Avenue construction begins, and establish a preventive maintenance plan to avoid recurring failures.
Brown told council he included a larger-than-normal contingency because crews may discover additional structural damage once the old brick is exposed. He said the city expects to start work within a week of approval, with the gate installation complete by mid-spring, and will use temporary fencing during demolition.
Council member Hennen and others praised the preparation and asked about outreach to adjacent neighbors; Brown said the project team will notify nearby residents of construction-related noise and dust and expects minimal day-to-day disruption. Brown also explained tuckpointing as the replacement of deteriorated mortar between bricks to prevent water intrusion and freeze-thaw damage.
The contract with Allied Building Services was approved subject to city-attorney review and execution by the city manager.
The contract award follows the council’s adoption of a budget amendment that allocates one-time funds to cover the repair and associated contingency. Staff will return documentation and any contract amendments to council if contingency use increases the project cost beyond the approved amount.

