Staff recommends awarding Memorial Gardens Phase 2 contract after low bid of $609,428

City Commission, City of Lake Wales · January 28, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public Works reported a low bid of $609,428 from Tiger Contracting LLC for Phase 2 of Lake Wales Memorial Gardens, roughly half the engineer's prior estimate; staff and the engineer reviewed the bid and recommended the commission award the contract.

Sarah Kirkland, the city’s public works director, told the commission the low bid for Phase 2 of the Lake Wales Memorial Gardens cemetery came in at $609,428 — substantially below a prior engineer estimate of about $1.2 million.

"The bid came in at $609,428 where we had previously estimated it was going to be somewhere around $1.2 [million]," Kirkland said, and noted staff and the project engineer reviewed the low bid to ensure bidders had not omitted required items. The engineer’s review and staff interviews indicated the low price reflected the bidder’s low overhead and mobilization costs and that the bidder was a local company based in Lakeland.

Kirkland said staff was recommending the commission award the contract to Tiger Contracting LLC. Commissioners asked whether bidders had known the city budgeted about $1.2 million; staff said the budget estimate was public in the city’s budget book and on the city website and that the engineer had used that amount as a probable construction cost when preparing estimates.

No formal award vote appears in the meeting transcript; staff made a recommendation for the commission to consider.