Commission approved Lindstrom Construction to insulate and finish the interior of a county building and tabled the floor installation quotes for a requested line-item comparison to ensure apples-to-apples bidding.
The Ramsey County Commission approved Lindstrom Construction’s quote to insulate and finish the interior of a county building, and directed staff to obtain clearer line‑item breakdowns on competing floor quotes before committing to floor work.
What was decided: After reviewing multiple bids, commissioners endorsed Lindstrom’s steel-finished insulation approach and accepted the bid for insulation and interior finishing. For the floor and mezzanine work, commissioners asked for a detailed, line-by-line bid comparison because the competing quotes differed significantly in scope — notably whether footings and floor heating were included — and tabled that portion of the work pending a revised, comparable estimate.
Financial and schedule notes: Staff said the building work will be funded from carryover ‘veil’ funds from last summer (roughly $400,000 remaining) and that construction scheduling will await the clarified bids. Lindstrom’s insulation/finish quote was the preferred option because it included a finished steel interior rather than spray foam without steel.
Next steps: Staff will request line-item revisions from bidders for the floor work and bring the updated comparisons to the commission. Lindstrom may begin the insulation and interior finishing work once administrative steps are completed.