Contractor says slab in ~90 days for Guthrie wrestling facility; pool punch list expected in September–October
Guthrie Public Schools Board of Education · March 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.
Summary
Crossland Construction representative reported that site and utility work began after weather delays; the contractor expects to pour a slab in about 90 days and aims for September–October completion for related pool work, subject to weather and site conditions.
At the Feb. 9 meeting the board received a construction update from Lane of Crossland Construction on the Guthrie wrestling facility project. Lane said site work and utilities began this week after…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans