Henrico supervisors approve appointments, permits and multiple contracts; introduce $34.4M in budget amendments
Summary
The board appointed members to the Sports and Entertainment Authority, approved a provisional use permit for Deep Run Roadhouse, conveyed park land to the SEA, adopted a building-line vacation, awarded sewer and stormwater contracts totaling about $6.8 million, introduced fiscal amendments totaling $34.4 million and authorized a major highway grant application.
Get email alerts on the Local Government Actions topic
No spam. Unsubscribe anytime.
At its Feb. 10 meeting the Henrico County Board of Supervisors approved a slate of administrative appointments and several board papers that included contract awards, a real property conveyance, and the introduction of February budget amendments totaling roughly $34.4 million.
Appointments and real property: The board appointed six individuals to the Sports and Entertainment Authority (board paper 44-26). The board also authorized conveyance of a parcel of Glover Park to the Sports and Entertainment Authority (46-26) to support a tournament facility; a county real property director said the transfer aligns adjacent parcels for the SEA's planned development.
Permits and ordinances: The board approved a provisional use permit (45-26) for outdoor food preparation and accessory outdoor dining at the proposed Deep Run Roadhouse (John Rolfe Parkway) subject to nine conditions (limits on smokers, screening of fuel/wood, prohibition on outdoor speakers and materials matching the shopping center). An ordinance (47-26) vacating a 50-foot building line at 6 Game On Road (River Hill subdivision) was adopted to allow front-porch improvements.
Contracts and capital projects: The board awarded a fixed-price $5,730,950 contract to In Situ Form Technologies for Phase 1 of the East Highland Park Sewer Rehabilitation project (50-26), with work expected to start in April and complete within 490 calendar days. It also approved a unit-price contract of $1,048,000 (plus a $155,000 allowance) to Harbor Dredge and Dock for the Ridgefield Parkway BMP and stream restoration project (51-26); the latter includes $168,000 in state contributions.
Budget introduction: Finance staff introduced February amendments to the FY25-26 plan (48-26) totaling $34,400,000; the presentation listed approximately $19,700,000 for four public works capital projects and cited operating requests including $3,000,000 for highway maintenance and $3,600,000 for General Services. The board set a public hearing on the amendments for Feb. 24.
Grant authorization: The board authorized public works to apply for a U.S. Department of Transportation grant (Better Utilizing Investments to Leverage Development build program) for a shore/pump-area improvements project with an estimated cost of $167,000,000 and an anticipated request of up to $25,000,000 in federal BUILD/BIL-era funds; county staff said about $60-65 million from CVTA and $32,000,000 from the state are already committed to the project.
Outcomes: All items on the consent/public hearings and general agenda described above were approved by voice vote without recorded roll-call tallies.
Votes at a glance (selected): - Appointments to Sports and Entertainment Authority (44-26): approved (sworn in) - Youngblood Properties rezoning (REZ 2025102326): approved (see separate article) - Deep Run Roadhouse provisional use permit (45-26 / PEP 2025102916): approved with conditions - Conveyance of Glover Park parcel to SEA (46-26): approved - Vacation of building line at 6 Game On Road (47-26): ordinance adopted - Budget amendment introduction (48-26): public hearing set; introduction approved - End declaration of local emergency for Winter Storm Fern (49-26): approved - East Highland Park Sewer Rehab contract (50-26): $5,730,950 award approved to In Situ Form Technologies - Ridgefield Parkway BMP & stream restoration (51-26): $1,048,000 unit-price award approved to Harbor Dredge and Dock - Authorization to apply for USDOT BUILD/BIL grant (52-26): approved
What happens next: The budget amendments proceed to a public hearing Feb. 24; contract award winners will coordinate with county staff on schedules and bonding/insurance requirements; planning and permit staff will monitor proffer and permit compliance where applicable.