County awards conservation-building repair and roof contracts to low bidders
Summary
The Board awarded two contracts for conservation building repairs and roof replacement: MCC Builders (part 1) for $22,510 and Webb Construction (part 2) for $35,804; the awards followed review of bid submissions and one disqualification.
Get email alerts on the Procurement topic
No spam. Unsubscribe anytime.
Facilities Director Chris Klub asked the board to award two contracts for conservation-building work split into part 1 (structural repairs and removal of two lean-to structures) and part 2 (roof replacement). Klub said five bidders attended mandatory pre-bid meetings and submitted proposals.
For part 1 the apparent low bidder was MCC Builders (Northfield) at $22,510; Klub noted Consulting Resources Group was disqualified from the part 1 award because their bid omitted required architectural repairs and only proposed removal of the two lean-to structures. The board moved, seconded and approved awarding part 1 to MCC Builders.
For part 2 (roof replacement) Webb Construction (Mankato) was the low bidder at $35,804; the board moved, seconded and approved awarding that contract as well.
Klub confirmed that one of the lean-to structures had already been removed and the master gardeners had relocated storage; the approved work does not include repainting of the two "ends" mentioned in questions from commissioners.
What happens next: Facilities staff will finalize contracts with MCC Builders and Webb Construction and oversee the work according to bid documents; staff noted scheduling and some non-covered repainting will be managed separately.
Votes and motions: Motions to award both parts to the low bidders were moved, seconded and carried by voice vote.