Nassau County previews Westside Regional Park opening and a slate of road, fire station and park projects

Nassau County Board of County Commissioners · February 26, 2026

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County staff reported progress on major capital projects, including Westside Regional Park (targeted opening this summer), County Road 107/CR‑121 improvements, Pages Dairy/Chester intersection, and several fire stations; staff requested consensus on cash carry‑forward allocations to catalyze signalization, trails and priority CIP items.

County capital‑projects staff reviewed the county's capital improvement program, showing current year construction, five‑year programmed projects and long‑range 20‑year planning. Presenters highlighted construction‑cost inflation in recent years (large increases in pavement, building, fire apparatus and ambulance prices) and identified both savings and additional needs across multiple projects.

Westside Regional Park: Staff displayed aerials from the construction site and said the project is about 75–90% complete in several elements; current estimates show approximately $750,000 in savings relative to prior budgets and an anticipated grand opening this summer. The park will include an amphitheater, an "airnasium," multiuse fields and trails, staff said.

Transportation projects: Staff reviewed urgent intersection needs — County Road 107/State Road 200, William Burgess Boulevard extension and Pages Dairy/Chester intersection among them — and asked the board to consider allocating approximately $1,000,000 for right‑of‑way work and $1,500,000 to signalize a key William Burgess/State Road 200 intersection. For the CR‑121 reconstruction (35 miles county‑maintained), staff proposed a $2.7 million change order to reduce detour lengths and improve public safety; presenters estimated the project would still close with roughly $765,380 in savings after the change order. Commissioners generally signaled support for prioritizing safety improvements.

Fire stations and public safety: Staff noted ongoing work on several fire‑station projects (Fire Station 30 replacement, Fire Station 70/90 updates, and other station maintenance), including some projected savings on negotiated contracts. The board also discussed staffing needs tied to new stations and evolving base levels of service.

Cash carry‑forward: Staff proposed allocating one‑time cash carry‑forward funds to an array of priorities (signalization for State Road 200 intersections, the 14th Street trail leveraging $5.2M in state funds, Westside campus planning, historic courthouse clock‑tower repairs and drainage projects). Commissioners gave consensus direction to proceed with recommended allocations and to return with formal documentation for adoption.

The board did not take final appropriations at the workshop; the session established priorities and directed staff to prepare formal agenda items and budget documents for future board action.