Conservation commission asks for riverfront mitigation and stormwater review on 1 Church Street redevelopment

Town of Northborough Conservation Commission · March 10, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Developers of a three-building mixed-use project at 1 Church Street agreed to provide a riverfront mitigation planting plan and a maintenance plan for permeable pavers; the commission continued the Notice of Intent pending Tetra Tech stormwater review and updated planting/maintenance details.

A proposal to build three mixed-use buildings at 1 Church Street — each with ground-floor commercial space and residential units above — drew detailed questioning from the Northborough Conservation Commission on March 9 because the site sits within a regulatory floodway, AE floodplain and riverfront buffer.

Daniel Sheehan of Haley Ward described the project layout and a StormTech subsurface infiltration system sized to manage runoff, saying the design was conservative and modeled permeable pavers as impervious to ensure the system accommodates worst-case runoff. "The system is designed to handle the hundred-year storm event," Sheehan said.

Glenda Williamson recommended the commission treat the site as a redevelopment under the Riverfront Act and asked the applicant to provide a mitigation plan that would improve existing degraded riverfront conditions — for example, wildlife‑friendly shrub plantings near the bank — and to add a brief maintenance plan for permeable pavers. "I would probably say that this could be qualified as a redevelopment in the riverfront area," Williamson said, and asked for plantings and an O&M plan for porous surfaces.

The applicants said they would provide a planting/mitigation plan and revise maintenance details for the pavers; the commission opted to continue the matter while awaiting a Tetra Tech third‑party stormwater review and the additional mitigation and maintenance details.

No decision was made at the March meeting; the commission asked the team to return with those details at the April meeting or after Tetra Tech completes its review.