Nags Head board approves $36.4 million award to Weeks Marine for 2026 beach nourishment

Town of Nags Head Board of Commissioners · February 4, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Town of Nags Head approved a notice of award to Weeks Marine for $36,412,600, authorized the town manager to execute the construction contract and adopted a capital project ordinance amendment to fund the 2026 beach nourishment project. Some public commenters questioned funding fairness.

The Town of Nags Head Board of Commissioners voted Feb. 4 to issue a notice of award to Weeks Marine Inc. for the 2026 beach nourishment project and authorized the town manager to execute a construction contract with the firm.

David, a town staff member presenting the item, said the board had previously authorized a notice of intent and that the next steps were issuance of a formal notice of award, contract execution and an amendment to Capital Project Ordinance No. 18 to include contingency, administrative and financing costs. He said the contract amount is $36,412,600 and that the town anticipates submitting the package to the Local Government Commission for review in April or May.

At public comment, resident John Cici said he had prepared a spreadsheet showing the project’s spending distribution and argued that the town would spend roughly one‑third of the $36 million on a single mile of shoreline, questioning whether property owners in that reach were paying a fair share. “That just does not seem fair to me at all,” Cici said.

Commissioners approved three separate motions at the meeting: to issue the notice of award to Weeks Marine, to authorize the town manager to sign the construction contract, and to approve Capital Project Ordinance Amendment No. 18 to allow for pre‑audit and to add contingencies and financing costs. The motions carried by voice vote with no opposition recorded in the transcript.

Town staff said the ordinance amendment will be updated as final contingency and financing numbers are pinned down and that the LGC review will follow the town’s submission. The board acknowledged significant planning and post‑storm urgency for the project but did not specify an exact construction schedule at the meeting.

The board’s packet and staff presentation include more detail about project reaches, budgetary assumptions and the capital ordinance language; the transcript notes the board will return with finalized contingency and financing figures prior to or during the LGC process.