Board staff recommend $830,389 contract for Longview Drive repairs and raise T-SPLOST program-management cap

Dawson County Board of Commissioners · March 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff recommended awarding an $830,389 contract to R and B Development for Longview Drive repairs (five deep 'pit' excavations, structural fill, overlay) and asked the board to approve raising the annual not-to-exceed for T-SPLOST program management services (BM&K and on-call engineers) to $350,000 from $250,000.

Public Works staff told the Dawson County Board of Commissioners they received eight bids for IFB 494-26 (Longview Drive roadway and drainage improvements) and recommended awarding the contract to R and B Development Inc. for $830,389 plus a 5% county contingency ($41,519.45). The project scope includes excavating five failed locations up to 10 feet deep, replacing with structural fill, repairing curb and drainage, and performing a deep patch and overlay. Etowah Water and Sewer also plans to relocate water lines affected by settling.

"We have received 8 bids and both staff and BMK have reviewed the bids. The lowest bid was almost 6% below the estimated engineering cost," Public Works Director Robert Drewy said. Staff said references for the recommended contractor were checked and looked favorable.

In related business, staff recommended amending contract #442-24 for T-SPLOST program management services (BM&K and on-call engineering) to establish a revised annual not-to-exceed amount of $350,000. Hannah told the board that in 2025 the category expended $504,130 (BM&K plus on-call engineering) and that the original $250,000 figure was an early, arbitrary limit. Commissioners questioned why the original limit was exceeded and whether there was a contingency; staff said there was no contingency in BM&K's contract and that a quarterly audit process will be implemented to monitor expenditures.

Why it matters: the award will move a locally significant road repair project toward construction with an identified contractor and budget. The contract amendment reflects higher-than-expected program-management use during the first year of program delivery and aims to prevent future unbudgeted overages by adding clearer contract limits and quarterly oversight.

Next steps: staff requested the board accept the bids and award the contract; they also asked the board to approve the contract amendment. No formal approval votes were recorded during the work session.