Engineers say Lake Placid wastewater plant largely built; training and commissioning remain

Lake Placid Town Council · March 10, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Engineers for the new wastewater treatment plant reported the physical construction is about 90–95% complete; remaining tasks include coatings repair, controls integration, operator training and plant start‑up. The contractor is late and liquidated damages will be enforced per the contract.

Pennoni engineers gave the council an update on the advanced wastewater treatment plant under construction, reporting that most physical work and equipment installation are complete and that the remaining tasks center on quality-control fixes, controls integration and operator training.

Roger Hellman of Pennoni told the council the project is about "90 to 95 percent" physically complete: structures and equipment are…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans