District says Verde project on track to start May 26 pending Riverside permit
Summary
Staff told the board they have the West 40 permit, are awaiting the Village of Riverside permit, will order equipment and make required 40% payments once permits arrive, and expect the Verde project to begin May 26 with weekly meetings during construction.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
A district administrator updated the board on the Verde project, saying the district has obtained a permit from West 40 and is awaiting a permit from the Village of Riverside. "Once we receive that, we will then go out and order all of the equipment," the administrator said, adding that a 40% payment will be required when equipment is purchased.
Staff estimated the project would likely appear on the March board meeting agenda for action related to funds and said the district remains on track to begin construction May 26. The administrator said project meetings will be weekly once construction starts and regular updates will come to the board at that time.