District: CTE building on schedule; nearly $9.94M spent to date

Louisa County Public Schools Board · March 4, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Facilities staff showed photos and construction milestones for the new CTE building, with steel installation slated to begin mid‑March; finance staff reported $9,935,363.83 spent so far and the project 34.45% complete.

District facilities staff (David, S6) updated the board on the new CTE building: block and CMU work is complete in many areas, classroom fit‑outs have started, and roof‑steel installation was scheduled to begin March 16 with membrane work to follow to make the roof waterproof.

Finance staff (S7) reported that $9,935,363.83 has been spent on the CTE building to date, which the finance presenter said represents 25.29% of the project budget and a completion status of about 34.45%. Staff said materials for remaining exterior strainers were staged and that specific tasks were scheduled to finish in the coming days.

Why it matters: The new CTE building is a near‑term capital opening the district expects to staff for August 27; the board discussed personnel additions tied to the facility and the need for continued budget monitoring.

Next steps: Staff will continue construction oversight and return with progress and budget reconciliations; the superintendent said the board should expect personnel requests tied to the new facility.