Council approves Crossland GMP for AC Kaplinger ballfield renovation; demolition expected soon

Edmond City Council & Public Works Authority · August 12, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a contract amendment with Crossland Inc. to begin demolition and earthwork for the AC Kaplinger Ballfield Complex renovation. Staff said design is 100% complete, the overall project budget is about $17.5 million, and early bids for demolition/earthwork came in below the 65%-design estimate.

The Edmond City Council on Aug. 12 approved a contract amendment with Crossland Inc., the construction manager-at-risk for phase 1 of the AC Kaplinger Ballfield Complex renovation, allowing demolition and earthwork to begin.

Brad Rainey, the city's parks and recreation director, told council staff had received 100% design documents and that the construction budget for the broader project was cited at $16,100,000 with roughly $1,300,000 for design and a total estimated project budget near $17.5 million. Rainey said the city split early work into demolition and earthwork so those portions could be bid and started sooner; those two elements came in under the budgeted estimate and, he said, "shortly after this meeting, probably a couple weeks, we will start to see demolition take place."

Rationale and schedule: Rainey said the renovation will reduce the number of fields, add parking, replace playgrounds and restrooms, add synthetic turf in some areas, and improve sidewalks and shade. A tentative ceremonial groundbreaking is planned for Sept. 10; staff expects to bring additional bid results and final contract packages back to council in October.

Vote and motion: Council made and seconded a motion to approve the contract amendment; the council voted to pass the item.

Next steps: Staff will finish its review of the 100% design, finalize a site plan, release remaining bid packages and begin demolition and earthwork as soon as the contracted work is mobilized.