Edmond staff update council on water plant, parks, police and fire projects
Summary
City staff reported timelines and budgets for major capital projects: water-treatment expansion (2030 target), YMCA/library construction (city $30M commitment; YMCA to repay $13M over 15 years), Pelican Bay pool replacement, a new fire station opened in August, and police training and lake-patrol facilities under design.
City staff gave the council progress reports on a string of capital projects and public-safety facilities during the strategic planning workshop.
Water treatment expansion: Chris Knifing, Director of Water Resources, said Phase 2 is under construction, Phase 3 100% plans were due for review the same week, and bidding is expected in spring/early summer with construction beginning next fall. "Projected completion, if all goes well, is in 2030," Knifing said, while…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat