Hudson County commissioners seek contract review after new warming-center HVAC failed during cold spell
Summary
Commissioner William O'Dea pressed the board to review contracts and potential legal remedies after a newly installed HVAC system at a county warming center failed during cold weather, leaving clients in under-heated rooms; county staff said temporary heaters were provided and technicians worked remotely to restore service.
Get email alerts on the Public Safety topic
No spam. Unsubscribe anytime.
Commissioner William O'Dea urged Hudson County officials on Jan. 9 to seek legal review of a contract after a newly installed heating, ventilation and air-conditioning system failed at a county warming center during recent cold weather.
O'Dea told the Board of County Commissioners that the system, which he said cost about $1.4 million and was completed in the summer of 2024, failed within its first winter of operation and left spaces used by residents and staff at temperatures he described as unsafe. "There's no reason one why such a new system should be down," O'Dea said, arguing the county should explore all remedies against the manufacturer and installer.
County staff and a vendor representative described troubleshooting steps and temporary measures. Ralph Sax said technicians "were communicating by phone and online" and were remotely troubleshooting the system before it was restored, adding the system briefly came up but "it crapped out again overnight." County personnel said portable heaters were brought into the facility while repairs continued.
The board's discussion focused on response timing and contractor obligations. O'Dea said the apparent delay in securing a technician with programming access was unacceptable and asked the Law Department to review warranties and service commitments. "We should seek any and all legal action that we may be able to take," he said.
Commissioner Al Cifelli and others asked staff to produce a clear timeline of vendor and manufacturer notifications and responses; Cifelli noted there is a legal difference between a strict-contractual liability and a claim of negligent response. Chief administrative staff said temporary heating units remain available at the site and the county would assemble the contract and service timeline for counsel to review.
The board did not take immediate formal action during the meeting beyond requesting that counsel and administration report back with contract details, timelines of vendor contact, and any warranty provisions that might apply. Staff said the building was fully heated at the time of the commission meeting and that a full review would follow.