Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Camp Verde council approves wastewater dryer contract, ratifies SCADA upgrade and awards sports-complex slab bid
Summary
The Camp Verde Town Council unanimously approved three infrastructure actions June 18: a wastewater sludge-dryer design contract not to exceed $85,049, ratification of a SCADA purchase order up to $120,000, and a $50,208 award for a sports-complex irrigation pump building slab.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Camp Verde Town Council on June 18 unanimously approved a package of infrastructure contracts aimed at upgrading the town’s wastewater operations and moving forward on sports-complex irrigation work.
Wastewater Division Manager Chet Teague told the council the largest item, Contract No. 25-209 with Water Works Engineers, covers engineering design and construction services for sludge-dryer units and a new septage-hauling station at the Town’s Water Reclamation Facility. Councilor Robin Godwin moved to approve the contract, Councilor Robert Foreman seconded, and the council approved the contract not to exceed $85,049 by a 7-0 roll-call vote.
Teague also explained an updated purchase order for the SCADA (Supervisory Control and Data Acquisition) upgrade, describing the vendor’s IT board as the project’s central control unit. Town staff requested ratification of Purchase Order No. 2025-0031 to Rottweiler Controls, LLC, to reflect additional upgrades. Councilor Jessie Murdock moved to ratify the purchase order; the motion passed 7-0. Town Manager Miranda Fisher said the ratification was needed so payment could proceed and the project remain on schedule.
Separately, CIP Project Manager Martin Smith recommended awarding Bid No. 25-211 for the concrete foundation and slab of a proposed irrigation pump building at the Sports Complex. The council voted to award the $50,208 contract to Ligon Excavation (motion by Councilor Robert Foreman, second by Councilor Brian Bolton), 7-0.
The measures were presented as routine capital and operational upgrades; council discussion focused on scope and timelines rather than contentious policy choices. The minutes do not list construction start dates or vendor delivery schedules.
Next steps: staff will execute the contracts and continue procurement and design work. Specific implementation schedules and any required permitting or inspections were not specified in the meeting record.
