Buffalo County approves multiple change orders and amends construction management agreement for 610 Central project
Summary
The Board approved several change orders for the 610 Central Project, accepted County Attorney amendments to the Construction Management at Risk Agreement with Beckenhauer Construction Company, and authorized purchase of a 2022 Ford F‑250.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
Facilities Director Steve Gaasch reviewed change order requests from Beckenhauer Construction for the 610 Central Project and the Board approved multiple items including additional wall demolition and framing, concrete repair at the fire line, added bollards and an electrical outlet circuit, a new electrical room per inspector, epoxy floor finishes in multiple rooms, and added fire alarm devices. Individual change order amounts were recorded in the minutes.
Commissioner Timothy Higgins moved and Commissioner Myron Kouba seconded to approve Change Order Requests #2–#7 with amounts recorded in the minutes: $3,990.74; $527.88; $2,768.18; $8,146.17; $2,503.19; and $1,333.42. The motion passed by recorded vote of present members.
The Board also approved purchase of one 2022 Ford F‑250 through the Nebraska state contract for $45,230.00 (moved by Higgins, seconded by Lynch) and accepted certain County Attorney recommended amendments to the Construction Management at Risk Agreement with Beckenhauer Construction Company; the Chair was authorized to sign the amendment. Deputy County Attorney Andrew Hoffmeister reviewed the Construction Management Agreement before the Board voted to amend it.
The minutes record the approvals and dollar amounts for the change order items, the vehicle purchase price, and that legal‑office suggested language changes were accepted; they do not list implementation timelines or contractor acceptance dates in the public minutes.