Chester County contractors outline 2025 paving schedule; some projects target late‑2026 completion

Chester County Transportation Committee · March 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County contractors told the Transportation Committee that one‑time and annual‑funded 2025 road projects are underway: patching begins this month, several roads are already paved, the program is about 55–56% complete, and contractors aim to finish major paving by Nov. 30, 2026.

County transportation contractors on Feb. 2 briefed the Chester County Transportation Committee on progress and schedules for the county’s 2025 road programs.

Brian Faulkenberry of Infrastructure Consulting & Engineering LLC (ICE) said patching on county‑maintained roads — Clara’s Court, Cloud Road, East Creek Road, Discovery Road, Hamilton Road, Huntington Drive and Rocky Creek Road — is scheduled to start this month, with paving to continue through June and into summer. Faulkenberry said the one‑time funded program has an overall project completion date of Nov. 30, 2026. He also noted two state‑maintained segments, Duke Street in Great Falls and the state portion of Quail Hollow Circle, are under separate contract to start in August and be completed by Sept. 30 (as reported to the committee).

Richard Turner of Morton Thomas and Associates (AMT) reported on the county’s annual funding road program and said it is about 55–56% complete. Turner said all three local roads in that package (McCree Drive, Hosea Strong Road and Looking Glass Drive) and two state roads (Martin Luther King Memorial Drive and Lowry Street) have been paved; final pavement markings are pending warmer weather. He told the committee that contractor King Asphalt plans to return to Chester on Feb. 23 to begin work on Enix Road and then proceed to Nelson Road, Sycamore Road and Lincolnville Road, aiming to finish around March 22. Turner added that the official contract completion date for the AMT package is May 31 and that progress remains dependent on weather.

Votes at a glance: the committee approved the Sept. 15, 2025 Transportation Committee meeting minutes by a 7–0 vote (motion by Vice Chair Erin Mosley; second by Councilman Bobby Raines). The meeting adjourned by a 7–0 vote later in the session (motion by Councilman Bobby Raines; second by Councilman Roy Bunson). The minutes also record the seconder on the adjourn motion spelled as “Brunson” in one segment; the committee roster lists him as Roy Bunson.

Why it matters: Chester County drivers and residents on the listed roads can expect staged patching and paving operations over the coming months. Several projects are tied to weather and contractor schedules; the committee was not presented with cost or contract amendment details during the update.

Committee follow‑up: contractors gave target dates for contractor returns and contract completion; the committee did not record additional council direction or formal changes to contract terms at this meeting.