Committee advances planning for CTH B reconstruction, structure designs and approves rout‑and‑seal on USH 8

Oneida County Public Works & Solid Waste Committee · March 1, 2026

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Highway staff outlined plans for a 1.05‑mile CTH B reconstruction in 2027, proposed bundling four structure designs (with a mussel survey estimated at $25,000), and the committee approved a WisDOT DMA to rout and seal a portion of USH 8 with an estimated cost of $70,000.

Highway Commissioner Alex Hegeman told the committee that 1.05 miles of County Trunk Highway B from STH G to USH 45 is scheduled for reconstruction in 2027 and recommended hiring an engineering firm to produce design and plan sets intended to prevent a permanent 5‑ton year‑round weight limit.

Hegeman said four structures currently rated 4 out of 10 could be bundled into a single design contract; the sites are within roughly a five‑mile radius, which would simplify bidding. He also said a mussel was observed in the stream on CTH E and that a mussel survey would be required, with two consultants identified and an estimated cost of about $25,000.

Separately, Hegeman presented a WisDOT design‑maintenance agreement (DMA) to crack seal USH 8 from CTH P to Forest with an estimated cost of $70,000. Robb Jensen moved and Dan Hess seconded approval of the DMA; the motion carried.

Committee members directed staff to proceed with drafting RFP documents for the CTH B design and for structure design work, and to include relevant environmental survey work in the bid packages. The committee did not vote on the RFPs at this meeting; the WisDOT DMA was approved as presented.