Fiscal Court approves bridge-project paperwork, authorizes RDAAP funds and schedules county clerk's office move
Summary
Simpson County Fiscal Court approved the Rural and Municipal Aid 80/20 Bridge Project resolution and agreement, authorized up to $16,000 in RDAAP funds for an industrial authority project, and confirmed a move into the new county clerk building with a public tour planned.
Get email alerts on the Infrastructure And Facilities topic
No spam. Unsubscribe anytime.
FRANKLIN, Ky. — At its Aug. 5 session the Simpson County Fiscal Court approved paperwork for a Rural and Municipal Aid 80/20 Bridge Project, authorized RDAAP grant funding for an industrial authority project and discussed the upcoming move into the county clerk's new building.
The court voted unanimously to adopt the 80/20 Bridge Project resolution and the related agreement and to authorize County Judge/Executive Mason Barnes to sign the documents. The resolution formalizes county participation in the bridge project and allows execution of the state/local funding agreement.
Separately, court members approved a resolution to use Rural Development Assistance and Appalachian Access Program (RDAAP) funds for a Franklin-Simpson (F-S) Industrial Authority project in an amount up to $16,000 and authorized the County Judge to sign. The minutes record the authorization as “up to $16,000”; specific project details were not included in the meeting excerpt.
Judge Barnes said the Fiscal Court will tour the new county clerk building the following week and that the clerk's office plans to move Aug. 20, temporarily closing for one day to transfer software and operations. County Clerk Austin Johnson asked the public for patience during the move. The court also discussed interlocal inspection agreements with neighboring counties that could allow local inspectors to perform work currently routed to the state.
Public Works Director Bobby Groves reported a short, single-day closure will be needed to replace drainage tiles on Kummer Road between Schweizer and Andrews; the work is expected to take three to four hours on a morning in the last week of August. OEM Director Robert Palmer announced the Garden Spot run scheduled for Saturday, Aug. 9. The court entered executive session later in the meeting and adjourned upon return.
All formal motions and approvals cited above were recorded as unanimous by the members present.