QK4 recommended and the Fiscal Court approved ASL Excavation as low bidder for FEMA-funded slide repairs and authorized advertising for a replacement Little Elk Road bridge. County share of large FEMA projects was noted (13% increase tied to higher bids).

The Spencer County Fiscal Court approved engineering recommendations for flood- and slide‑repair projects and authorized a bridge solicitation on June 7.

Engineer Eric Bean of QK4 told the Court that FEMA-funded repair bids for Brashear’s Creek and East River Road slides and a smaller Little Mount Church repair were received; the apparent low bidder across those projects was ASL Excavation with a total low bid near $790,533.30 (packet text compares ASL’s bid to FEMA’s initial estimate). Because Brashear’s Creek and East River Road qualified as FEMA “large” projects, QK4 advised FEMA would consider cost adjustments so the county could accept the low bid; Little Mount Church’s small‑project overage was minimal. The Court voted to approve QK4’s recommendation and accept the low bidder pricing, noting that Spencer County’s 13% local share must be adjusted upward to reflect the higher bid.

In a related item QK4 recommended replacing the Little Elk Road bridge over Elk Creek after inspecting high-water damage and recommending a reduced-load posting; the engineering firm estimated a replacement bridge cost of approximately $249,600 and asked permission to advertise for construction bids with an alternate for modular block wall and approach work. The Court authorized release of the advertisement for bidders to replace the 40‑foot span and to bid roadway approaches as alternates. The solicitation packet requires KYTC prequalification or demonstrated similar experience, and contract bonding.

The Court’s approval moves both repair construction and the bridge replacement project into the procurement phase; federal reimbursement, project eligibility and the county local-match percentage will be reconciled as bids and FEMA guidance are finalized. QK4 and county staff will handle bid advertisement and subsequent contract-award actions.