Planning director: trail retaining walls must be rebuilt; RFP released for next phases; county forming materials management committee

Charlevoix County Planning Commission · March 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff reported retaining-wall problems on Phase 3 of the Boyne City–Charlevoix Trail requiring spring rebuilds, issued an RFP for engineering services for Phases 4–5 with a Jan. 24, 2025 deadline, and is convening a County Materials Management Planning Committee to prepare a new solid waste plan.

Planning Director Kiersten Stark updated the commission on several active county projects on Jan. 9.

Trail construction: Stark said that Phase 3 of the Boyne City–Charlevoix Trail has retaining walls placed too close to the paved path; five, possibly all six, walls will need to be rebuilt in spring. Once the walls are rebuilt, remaining construction items — paving, concrete work, bench installation, permanent signage and site restoration — will be completed. Construction is on winter hiatus and will resume in spring.

RFP for Phases 4 and 5: County staff finished preparing and released a Request for Proposals for engineering services for Trail Phases 4 and 5. A mandatory pre‑submittal meeting was held Dec. 10; staff are maintaining a running Q&A for proposers. The submittal deadline for engineering proposals is Jan. 24, 2025.

Materials management planning: Staff are working with the County Administrator’s office and Networks Northwest to establish a County Materials Management Planning Committee to oversee development of a new Solid Waste/Materials Management Plan to comply with new state statutory requirements.

Local grants and projects noted by commissioners included a University of Michigan wave‑generator prototype on Beaver Island supported by a $3.5 million National Science Foundation grant, and a $55,000 grant to reduce shipped solid waste on Beaver Island by approximately 30 percent; the latter will fund household compost bins for the island. Commissioners also reported an $8 million school bond approved by the Charlevoix School Board for the May election and ongoing local planning and legal activities in Marion Township.