County commissioners approved a $31,438.62 engineering addendum for Puckett Park (SPLOST VI) and issued a Notice of Award to Standard Contractors, Inc. for $351,126.78 for construction, to be funded with ARPA and SPLOST VI.

Tift County commissioners authorized a contract addendum and issued a construction Notice of Award for improvements at Puckett Park during their June 12 meeting.

County Manager Jim Carter said an addendum to the contract with Watkins & Associates, L.L.C. is needed so the firm can perform additional engineering work on the Puckett Park Improvement Project; engineering costs are $31,438.62 and will be paid from SPLOST VI. The addendum was approved by motion (seconded) and carried 6-0.

Bids for the construction work were opened June 5; Carter said there was a single bidder, Standard Contractors, Inc., at $351,126.78. He said the project will be funded with American Rescue Plan Act (ARPA) dollars and SPLOST VI and that staff will separately solicit bids for playground equipment. The board authorized issuance of the Notice of Award and directed the chairman to execute the construction contract; the motion carried 6-0.

The record shows staff will manage procurement of playground equipment separately and the County Engineer recommended proceeding with the lone bidder on the construction contract.

The board's actions commit county funds from SPLOST VI and ARPA for design and construction; exact timing for construction work and equipment procurement was not specified at the meeting.