Commissioners accept INDOT low bid and greenlight bridge and paving work

Dubois County Commissioners · June 17, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board accepted a $1,113,981.75 low bid from C&R Construction for INDOT CCMG work, approved a Castlen Steel rebar quote for bridge stockpile, closed Bridge #254 for a two-month replacement, and reviewed a multi-week chip seal and paving schedule.

Dubois County commissioners on June 17 accepted the low bid from C&R Construction for INDOT CCMG 2024-01 and approved related highway procurement and project schedules.

Highway Engineer Brent Wendholt reported C&R Construction submitted the low bid of $1,113,981.75 and the board accepted the bid and presented Bid Form 96 for signatures. Wendholt also requested replenishing the Bridge Crew’s rebar stockpile and presented multiple vendor quotes; the board approved a $34,076.00 quote from Castlen Steel.

Wendholt reported Bridge #254 (St. Anthony Road West) was closed on June 17 to tear out the existing structure and scheduled pile driving for June 24; the project is expected to take approximately two months. He also described a Meridian Road speed study that supported a 45 mph limit and noted HB 1090 grants the commissioners authority to adjust speed limits; the board kept the limit at 45 mph.

The Highway Superintendent, Steve Berg, provided a chip seal paving schedule and said projects are 33% complete with costs running below estimates; several overlay and paving dates through July and August were discussed.