Committee hears $60,000 redesign bid and $800,000–$1,000,000 repair estimate for Wheel Way; Tri-County bid noted for Site 6 repair
Summary
In new business the committee reviewed a Mashon Engineering $60,000 redesign bid for Wheel Way and repair cost estimates of $800,000 to $1,000,000; the meeting also recorded approval for a Site 6 repair and noted Tri-County received a bid. The transcript does not record formal vote tallies for these items.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Committee members discussed multiple maintenance and repair items affecting parks and trail infrastructure.
In new business the transcript records a Mashon Engineering redesign bid for the Wheel Way of $60,000 and projected repair costs between $800,000 and $1,000,000 to address metalwork and associated disrepair. The transcript attributes those figures to the Wheel Way repair update but does not record additional details such as a motion authorizing spending, a funding source, or a formal vote tally.
Separately, the minutes record an approval for a 'site 6' repair and note that Tri-County received a bid related to that site. The transcript records the approval line and the existence of a bid but does not provide a dollar figure or identify who moved or seconded any motion connected to the Site 6 item.
The manager also reported routine facilities issues that could affect near-term maintenance needs, citing an old, leaking roof at Whiting Hall and plans for a deep sink and commercial faucet as part of spring preparations. Staff reported removing substantial amounts of broken concrete from the campground shoreline and said additional cleanup remains.
Committee members discussed a possible five-year evaluation of trail health to guide future maintenance planning. The record does not show whether the committee approved funding for redesign, repair, or the five-year evaluation during this meeting; the transcript shows discussion and estimates but no recorded vote tally.