Dubois County awards Bridge #254 pile-driving contract to meet schedule, warns motorists of temporary closures

Dubois County Commissioners · June 3, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Commissioners awarded the pile-driving contract for Bridge #254 to E&B Paving to keep the replacement on an accelerated timeline and approved the INDOT CCMG contract; the highway office also reported ongoing chip-seal work and said work zones may be closed temporarily when drivers ignore flaggers.

Vice President Nick Hostetter and the Dubois County Commissioners awarded pile-driving work for Bridge #254 to E&B Paving after Highway Engineer Brent Wendholt said E&B could meet the project timeline.

Wendholt presented three pile-driving quotes and advised the county that CLR, Inc. (lowest bidder on price) could not begin until September, while Blankenberger Brothers provided a flat quote but had different availability. E&B Paving’s mobilization estimate and time-and-materials option made it the only contractor able to work in late June or early July, so the commissioners approved Wendholt’s recommendation; the motion carried 2-0.

Wendholt also presented the INDOT Community Crossings Matching Grant (CCMG) 2024-01 contract and requested authority to sign on the county’s behalf. The commissioners approved the contract and authorized Wendholt to sign it, voting 2-0. The CCMG paving project bids were later opened and read; bids will be taken under advisement and awarded at the June 17, 2024 meeting.

County Highway Superintendent Steven L. Berg reported progress on chip-seal overlays, noting completed work on CR 200 W and Old US 231 and planned work at sites including Holland Dumpster, Man Acres near Old Huntingburg Road, and the Ireland area; the Haysville Dumpster site was scheduled for preparation and paving midweek.

Berg said crews have encountered a growing number of motorists ignoring marked work zones and passing flaggers. For crew safety, the department will close work areas until a section is completed, and delays should be expected. The Highway Department posts a schedule of locations on the county website under the Highway Department drop box.

The county also accepted Phase 2 of the countywide bridge inspection and the draft report submitted by the inspector; the commissioners voted 2-0 to accept the report. The acceptance and the pile-driving award aim to keep the Bridge #254 replacement on the earlier schedule despite contractor availability challenges.

The bids for CCMG 2024-01 opened at the reconvened meeting and included CalCar Paving, J.H. Rudolph, E&B Paving and C&R Construction; the commissioners will consider award at the June 17 meeting.

Next steps: E&B Paving is expected to perform pile driving in late June or early July; formal award of CCMG paving contracts is scheduled for June 17, 2024.