Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the CDBG topic
No spam. Unsubscribe anytime.
Ware County proposes adding Dusty Lane and Katie Lane to 2023 CDBG Phase 2
Summary
Staff proposed using $267,144.12 in under-budget CDBG funds to add Dusty Lane and Katie Lane to the 2023 project; the county would contribute $26,196.88 and staff will coordinate pole relocations with the power company. The item was added to the regular meeting agenda.
Get email alerts on the CDBG topic
No spam. Unsubscribe anytime.
County staff proposed adding Phase 2 to Ware County’s 2023 CDBG project to include Dusty Lane (TA #2) and Katie Lane (TA #3), citing an under-spend of $267,144.12 in the original project that DCA approved for additional work.
County Manager James Shubert told the commission the county would be required to contribute $26,196.88 and that once Phase 2 is bid it could fall within the available budget. Staff noted three power poles sit in the county right-of-way and the power company should move them; the contractor's estimate included $5,000 per pole but the county manager expects the actual cost to be closer to half that estimate. The board added the Phase 2 addition to the regular meeting agenda for formal approval and instructed staff to contact the power company regarding pole relocation.
