Durham commissioners approve multiple capital and budget amendments, including sewer and pump station projects
Summary
At the Nov. 12 meeting the Durham Board approved several consent items including contract renewals and capital project amendments for Snow Hill Road Pump Station, Page Park Lift Station, Slater Road lift-station projects, and other infrastructure items totaling tens of millions in updates to project budgets.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Durham Board of County Commissioners approved a broad package of consent items and budget amendments during its Nov. 12 regular session, advancing several county infrastructure projects and contract renewals.
Among the approvals were a $313,288.87 contract with NWN to renew support for Cisco network and security equipment and multiple capital project amendments: Snow Hill Road Pump Station (Capital Project Amendment No.25CPA017) increased by $6,659,581 to a revised project budget of $36,954,581, including authorization to execute a design‑builder Guaranteed Maximum Price (GMP) amendment; Page Park Lift Station (25CPA-19) received an appropriation increase of $4,021,221 for a new total project budget of $4,236,671; and Slater Road lift station, force main and outfall projects were increased by multi‑million dollar amounts (25CPA-20) to reach updated budgets in the millions.
Other approved items included a FY25 Durham Transit Work Program Q2 amendment ($3,861,058), engineering services contracts for sewer improvements and lift station flow meters, and a $1,000,000 appropriation for the Seaton Road maintenance facility capital project (25CPA-21). Several budget ordinance amendments were adopted to reflect these changes in the FY 2024–25 budget.
Board votes on consent items were recorded as unanimous for the items taken up that evening. Details of each approved ordinance and capital amendment are part of the public record and listed in the meeting packet.
Next steps: Project teams and authorized contractors may proceed under the adjusted budgets and contract amendments; departments will implement work per contract terms and report back through routine county project oversight and procurement channels.