Morton County approves Knife River hauling bid and selects AE2S for Summit Avenue reconstruction engineering
Summary
The commission accepted Knife River Corporation's bid for gravel hauling ($169/hour per truck; $550/day mobilization) and approved AE2S for construction engineering on Project SC-3004(054) PCN 23864 — Reconstruction of Summit Avenue/County Road 140 in Hebron; both motions passed unanimously.
Get email alerts on the Contracts Public Works topic
No spam. Unsubscribe anytime.
The Morton County Commission voted March 13 to accept a bid from Knife River Corporation for contract gravel hauling at a rate of $169 per hour per truck and $550 per working day for mobilization.
Commissioner Buckley moved to accept the Knife River bid and Commissioner Tokach seconded; the motion carried with all voting aye.
The commission also approved the selection of AE2S as the construction engineering firm for Project SC-3004(054) PCN 23864 — the reconstruction of Summit Avenue/County Road 140 in Hebron. Commissioner Tokach moved for the selection and Commissioner Morrell seconded; the motion carried unanimously.
The meeting record does not include contract award details beyond the bid rates and the selected firm; no project contract amounts, start dates or specific scopes beyond the PCN and project description are provided in the minutes.