County approves easement, structure contract and coordinates with pipeline on Road 13 bridge replacement

Union County Board of Commissioners · February 17, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Superintendent Buum presented and the board approved a temporary easement for CR #15 reconstruction and a construction agreement with Katzer Concrete for Structure 64-080-034; officials also noted posted load limits and held a conference call with Northern Pipeline about a gas main near a 2027 bridge replacement.

Union County commissioners approved multiple highway-related actions and discussed pipeline coordination at their Feb. 17 meeting.

Superintendent Buum presented a voluntary right-of-way agreement for CR #15 with Larry and Tami Orr that includes a 0.156-acre temporary easement; the board approved the agreement and authorized signatures. The board also approved a construction agreement with Katzer Concrete Inc. for Structure 64-080-034 and was informed that load limits were posted on county roads on Feb. 17.

Separately, State's Attorney Zenner and the commissioners conducted a conference call with Northern Pipeline to discuss moving a gas pipeline that lies near a bridge on county Road #13, a bridge replacement project scheduled for 2027; coordination and timing were discussed to allow the bridge replacement to proceed.

All motions on these items were recorded as carried in the minutes; the document does not record roll-call vote tallies.