Snowflake approves $129,000 sewer repairs on 1st East to correct reverse flow

Town Council, Town of Snowflake · March 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Town staff presented a plan to replace three manholes and roughly 600 feet of sewer pipe on 1st East at an estimated cost of $129,000, including street repairs; council approved the project unanimously Nov. 5.

The Snowflake Town Council unanimously approved a staff recommendation on Nov. 5 to replace three sewer manholes and about 600 feet of sewer pipe on 1st East to correct a reverse-flow condition in a system installed in 1974.

Brian Richards presented the problem to council, saying the town identified the reverse flow and recommended replacement of the affected infrastructure. He gave the cost estimate at $129,000, which includes subsequent street repair after construction. Councilmember Cory Johnson moved to approve the work and Lora Jones seconded; the motion passed unanimously.

Council documents and staff comments indicated confidence that replacing the three manholes and the identified length of pipe will resolve the reverse-flow issue, with some additional small fixes noted during the assessment. The council did not attach additional conditions to the approval.