Commission approves Kopper Glo Mining permit for Creek Road in Ninth District
Summary
Claiborne County Commissioners unanimously approved Resolution 2019-097 allowing Kopper Glo Mining, LLC to permit and bond 2.1 miles of Creek Road (Ninth District); the company will maintain the section and the road will remain permanent post-reclamation.
Get email alerts on the Land Use topic
No spam. Unsubscribe anytime.
The Claiborne County Commission approved Resolution 2019-097 on Dec. 16, permitting Kopper Glo Mining, LLC to permit and bond a 2.1-mile section of Creek Road in the county’s Ninth District. The described segment begins at the southwestern end of the existing concrete bridge over Straight Creek and extends roughly 2.1 miles to the intersection with Haul Road '1R.'
According to the resolution language, Kopper Glo Mining will perform maintenance and repairs on the permitted and bonded section on a schedule the company says will be timelier than the county highway department’s routine schedule. The resolution states the road will remain a permanent road after mining and reclamation are complete. The motion carried on a 20–0 roll-call vote.
There was no separate recorded amendment to the resolution at the meeting beyond an earlier agenda clarification to rename the road to 'Creek Road' to avoid confusion with Straight Creek Road. Commissioners did not attach additional environmental controls, bonding amounts, or inspection schedules in the motion as recorded in the meeting minutes. The resolution instructs the road superintendent to process the permitting and bonding as requested.