Snowflake council approves Circle K traffic escrow, paving and utility contracts; adopts tentative budget

Town of Snowflake Town Council · March 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Town of Snowflake approved a Circle K escrow agreement to fund a traffic signal at Main and Snowflake Blvd (approx. $382,000), contracted W.W. Clyde for asphalt work and Apache Underground for two manhole replacements ($118,560), and approved the FY25-26 tentative budget and a town-attorney contract.

The Snowflake Town Council on May 6 unanimously approved a series of development and infrastructure actions, including an escrow agreement with Circle K to fund traffic-signal improvements at Main Street and Snowflake Boulevard, authorizing a paving contract with W.W. Clyde and a two-manhole replacement contract with Apache Underground.

Brian Richards, town staff, summarized a traffic study and said the Circle K development will work with the town on intersection changes and that funds would be placed in escrow for construction; the council approved Resolution 2025-05 to accept the agreement. Richards described the escrow as "Approx. $382,000." Councilmember Byron Lewis moved the resolution; Mark Sheen seconded and the motion passed unanimously.

On capital projects, the council approved a FY24-25 asphalt paving contract with W.W. Clyde after staff recommended the company as both cost-effective and local. Mark Sheen called the projects "big wins for the town," and the council approved the contract by motion.

For sanitary infrastructure, staff reported that three manholes already had been replaced and two additional manholes (1st E & 4th S, and 9th S & Main St) need full replacement rather than epoxy repair. Staff recommended Apache Underground at a bid price of $118,560 for full replacements. Cory Johnson moved the Apache contract; Reid Stinnett seconded and the council approved the contract unanimously.

The council also adopted the FY25-26 tentative budget by motion. Brian Richards said the tentative budget sets a maximum spending level and that the town will return with a public hearing and a final budget adoption, likely in July.

Finally, the council approved contracting with Pierce Coleman PLLC to serve as town attorney with Robert Wingo assigned to the account. Council discussion noted the value of outside counsel with fewer local conflicts; the contract includes a $5,000 monthly fee with additional services billed separately. Joe Bjornn moved the contract; Reid Stinnett seconded and the motion passed unanimously.

Votes at a glance: Consent agenda approved (motion by Travis Kay, 2nd Joe Bjornn; unanimous with Cory Johnson absent); Resolution 2025-05 (Circle K escrow) approved (motion by Byron Lewis; unanimous); land-trade motion (decline current options but authorize mayor and vice-mayor to continue talks) approved (motion by Travis Kay; unanimous); W.W. Clyde paving contract approved (motion by Mark Sheen; unanimous); Apache Underground manhole contract approved (motion by Cory Johnson; unanimous); FY25-26 tentative budget approved (motion by Byron Lewis; unanimous); Pierce Coleman PLLC town-attorney contract approved (motion by Joe Bjornn; unanimous).

The council indicated several follow-up tasks for staff, including implementing contracts, coordinating Circle K's improvements, and scheduling the budget public hearing.