Camp Loreagle scales back plan; seeks craft‑center addition and staff housing, county emphasizes engineered plans and septic approvals

Benton County ERC (technical review) · November 12, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Camp Loreagle told Benton County it pared a multi‑year plan to a one‑year submission focusing on a craft‑center addition (~1,000 sq ft interior) and a two‑story staff housing building with walkout basement; staff said the craft center is assembly use requiring engineered/stamped plans, state plumbing letters or DEQ approvals and fire life-safety documentation, and noted fire-water/hydrant access questions.

Camp Loreagle representatives told the county they reduced a previously broader capital plan to a single-year submission that focuses on two projects: a craft-center addition (roughly 1,000 sq ft of enclosed interior space and about 1,000 sq ft of covered exterior seating) to support summer programming, and a two-story staff housing building adjacent to the health center to provide sleeping space for nurses and medical volunteers and to expand designated storm-shelter capacity.

The camp said it will not expand camper capacity; operationally the camp runs about 750 campers in summer and fields around 300 seasonal staff. For the craft center, building-safety staff said the use is an assembly occupancy and therefore requires structural-engineered plans, stamped MEPs and a state plumbing letter; DEQ involvement was noted for the camp’s wastewater permit, which remains the camp’s regulating authority for wastewater. Fire staff emphasized the need for a fire and life-safety plan and asked applicants to confirm nearest hydrants: the on-site well cannot support a sprinklered assembly and the camp said it is investigating a holding-tank and pump solution.

911 staff confirmed addressing and requested the applicants use the addresses the county previously issued; planning staff noted setbacks, buffering and that permanent parking may not be required because camp activity is controlled and shuttled. County staff said they will provide a checklist and that inspections and stamped sign-offs will be needed prior to occupancy/use for public events.