Prosper authorizes $1.76 million change order to install well and service at Raymond Community Park
Summary
The council authorized change order No. 5 to install a well and electrical service at Raymond Community Park, not to exceed $1,757,450, after staff reported competitive bids and discussed uncertainty about electrical service timing and a TCEQ permit that currently limits approved pumping to 9 million gallons per year.
Get email alerts on the Parks Infrastructure topic
No spam. Unsubscribe anytime.
The Prosper Town Council authorized a change order to install a well and electrical service at Raymond Community Park, approving an amount not to exceed $1,757,450 to move the work forward.
Staff told the council the project had been bid and one responsive bid came in at about $1,372,450, lower than the previous placeholder estimates. The change‑order request includes the well installation, pumps and a conservative allowance for electrical service design and construction; staff inserted a $300,000 placeholder for electrical service while awaiting final cost estimates and noted they expect the actual electrical cost to be lower in many scenarios.
Staff also updated the council on the TCEQ water‑use permit: the town requested roughly 28 million gallons per year but TCEQ approved 9 million gallons; staff said they plan to pursue appeals or updated requests after they collect summer pumping data to support a higher allocation. "We were approved for 9,000,000; we believe we need about 28,000,000," staff told council, adding that appeals are possible and typical in that process.
The council passed the authorization for the change order unanimously. Staff said the work would keep the Raymond Community Park schedule on track, with an estimated completion window for the larger park project in the late April–May timeframe depending on ancillary utility timing and contractor scheduling.
What’s next: Staff will execute change order No. 5, continue coordination with the electrical utility for service design and cost, and pursue further permitting or appeals with TCEQ as appropriate.