Courthouse steps remodel to be bid this winter with projected completion June 30, 2026
Summary
County officials reviewed proposed courthouse steps and landing plans. A pre-bid conference and bid opening were scheduled for late January and early February, with award targeted Feb. 11 and completion projected for June 30, 2026.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
A virtual walkthrough of plans to replace the courthouse steps and landing was presented to Garfield County commissioners on Jan. 7, 2026.
Brandon Janshen reviewed the existing conditions and the proposed design for the new steps and landing. He provided a project schedule: final review of drawings and specifications on Jan. 14 at 11 a.m.; a video pre-bid conference on Jan. 29 at 11 a.m.; bid advertisements to run on Jan. 12, Jan. 26 and Feb. 2; bid opening on Feb. 4 at 11 a.m.; and an award decision slated for Feb. 11. The projected completion date for the project is June 30, 2026.
No formal award or contract was decided at the Jan. 7 meeting; the board recorded the timeline for procurement and directed staff to proceed with the advertised schedule.