Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Facilities And Operations topic

No spam. Unsubscribe anytime.

Library director reports progress on Farmington branch construction, Twig temporary branch sees strong early use

Davis County Library Board · March 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Director Josh Johnson told the board that pre-construction on the new Farmington branch is nearly finished (asbestos abatement underway, permit submission planned for April 2 and construction expected to begin in May) and that the temporary 'Twig' branch is averaging over 100 patrons per day with programs resuming in April.

Library Director Josh Johnson and staff updated the Davis County Library Board on March 12 about progress on the Farmington branch pre-construction and the early operations of the Twig temporary branch.

On the Farmington project, staff reported a fence is in place around the building and asbestos removal is underway. The team plans to submit for the contractor’s permit on April 2, move the CM/GC subcontract bidding process into April and May, and begin construction in May; staff estimated the build will take about a year. "The asbestos removal team's been in there. They should take about a month," a staff member said, and the board discussed permitting and budget implications.

Staff also described salvaging legacy children's tiles from the previous building and placing them in a book at the Twig for patrons to review and claim; approximately nine tiles were recovered and will be available for pickup at the Twig. The board discussed how to handle unclaimed tiles and possible ways to incorporate a commemorative element in the new building.

The Twig temporary branch opened to the public recently and staff reported healthy early traffic: daily patron counts have exceeded 100, with about 140 visitors on the first day. Staff plan to resume story time next week and restart additional regular programs on April 1. Johnson said staff are exploring outreach at Main Street events and a limited-edition bag giveaway for the first 150 families at the grand-opening event noted in the meeting.

Staff also reviewed options for additional temporary sites: the Bountiful off-site location lease runs through the end of quarter four 2027 with options to change timing, and a possible North Salt Lake temporary site of roughly 1,000 square feet is under consideration; staffing and facility department workloads make firm decisions unlikely before June.

The board praised staff work on making temporary services available and on pre-construction planning. The meeting adjourned at 1:47 p.m.

Quotes are taken directly from the March 12 meeting transcript and attributed where speakers were identified in the record.