Summary
Bond project manager reported steel erection and slab pours at Vidor Middle and Oak Forest Elementary; trustees authorized relocation of a fiber optic line for the Vidor Elementary addition to be paid from the bond owner contingency fund.
The VIDOR ISD bond-construction update at the Oct. 13 board meeting showed recent milestones and identified a required fiber relocation tied to an elementary-school addition.
Mr. Bennett reported roughly $4.5 million in recent costs concentrated at Oak Forest Elementary and Vidor Middle School and said steel erection has begun on the middle-school 300 wing while slab work and preparatory activity are underway at…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat