Lynndyl hears update on new well; council to weigh contingency funds for fencing, valves and tank cleaning
Summary
Sunrise Engineering told the council the new well startup and component testing succeeded; the town has about $151,254 in contingency funds and members discussed bids for perimeter fencing, pond fencing, 10-inch valve replacement and tank cleaning, with a decision deferred to the October meeting.
Sunrise Engineering told the Lynndyl Town Council that the new municipal well has completed startup testing and that building components and the pump appear to function as intended, but the town still must secure an operating permit and finish a drinking-water-source protection plan before the new source can be turned on.
Presenter (S5) said bacterial samples for the new well have passed, and the firm’s hydrogeologist is expected to finish the…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat