Council awards culvert repair contract after 72-inch culvert failure; project budget set at $225,500

Newton City Council · March 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After a 72-inch CMP culvert failure, council awarded a $157,800 construction contract to Kemp Sigmon Construction and adopted a budget ordinance establishing a $225,500 project fund that includes contingency and engineering costs.

Newton City Council on Nov. 10 awarded a construction contract to repair a failed 72-inch corrugated metal pipe (CMP) culvert at North Frye and West 24th Street and adopted a budget ordinance establishing a capital project fund for the work.

Public Works and Utilities Director Dusty Wentz said the culvert failed on Aug. 16, 2020, creating a sinkhole adjacent to West 24th Street and a nearby gravity sewer line. The city solicited bids and received the following: Kemp Sigmon Construction $157,800; M&M Construction $178,340; and Hickory Sand Company $196,455. Wentz recommended the low qualified bidder, Kemp Sigmon, and asked council to adopt a total project budget that rounds the estimate to $225,500 to cover construction, 10% contingency, project engineering, and an unplanned excavator rental.

Council approved a Resolution of Intent to Reimburse, awarded the construction contract to Kemp Sigmon Construction Co., Inc. for $157,800, and adopted the budget ordinance to establish a West 24th Street Culvert Replacement capital project fund with an estimated total cost of $225,500. The contract award and budget ordinance were approved unanimously on motions from Council Member Jody Dixon.