Downtown Cramerton streetscape near completion; furniture to be placed in 2–3 weeks
Summary
Project days 81–96 saw concrete pouring completed and decorative railings installed; Mr. Sturgis reported that received furniture will be assembled and placed in the next two to three weeks, bringing the project close to completion.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
Mr. Sturgis updated the Town of Cramerton Board of Commissioners on the Downtown Streetscape project at the Nov. 5 workshop. He reported that concrete pouring for project days 81–96 has been completed, decorative railings are being installed, and the furniture has been received.
Mr. Sturgis said the project is nearly complete and that the furniture will be assembled and placed in the next two to three weeks. No budget revisions or schedule changes were recorded in the minutes; the update indicates completion is imminent but does not provide a final opening date.