Trustees approve construction contract items and change orders, accept completion of Torrey Pines Phase 1

San Dieguito Union High School District Board of Trustees · March 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board authorized a contract with LA Propoint Inc., approved a final deductive change order that reduced Torrey Pines Phase 1 GMP by $289,751.41 (revised GMP $11,699,158.22), accepted Phase 1 as complete and authorized release of retention to C.W. Driver, LLC, and approved a $249,897 change order to install gas piping for SDA welding stations.

The San Dieguito Union High School District Board of Trustees approved a set of Business Services actions Feb. 12 that affect ongoing capital projects across the district.

Key actions recorded in the minutes include: adoption of Resolution R2025‑2026/36 authorizing a contract with LA Propoint Inc. to furnish labor, materials and equipment to perform rigging repair and any additional inspections needed; approval of a final deductive change order for Phase 1 of the Torrey Pines High School (TPHS) Athletic Facilities Improvements Project (CB2023‑05) that decreases the Phase 1 amount by $289,751.41, yielding a revised Phase 1 Final Guaranteed Maximum Price of $11,699,158.22; acceptance of Phase 1 as complete and authorization for staff to file a Notice of Completion and release remaining retention to C.W. Driver, LLC; and approval of a $249,897 change order increase for Phase 2A of the San Dieguito High School Academy (SDA) Modernization Project (CB2024‑03) to add gas piping infrastructure supporting new TIG and MIG welding stations in the Building I Metal Shop.

Board motions were recorded as moved by Rimga Viskanta and seconded by Jodie Williams, with the board recording unanimous yes votes on the listed Business Services items. The minutes state that Stephen Dickinson, Associate Superintendent of Business Services, is authorized to execute required documents on behalf of the district for the listed contracts and change orders.

The minutes do not publish contract award amounts for LA Propoint Inc. nor specify retention totals to be released to C.W. Driver, beyond the change order figure and the revised Phase 1 GMP included above. The district’s capital budget impacts for the SDA gas‑piping change order and other items were not itemized in the minutes provided.

Next steps: Staff were authorized to execute contract documents and to file the Notice of Completion for Phase 1 TPHS; the minutes do not list further board review dates for these specific contracts.