Road Department reports successful asphalt runs, beaver‑mitigation work and upcoming pavement markings; commissioners approve contract COLA and release of bond
Summary
Road Department manager Dave Prunty reported an accurate asphalt mix after plant upgrades, winter readiness with salt‑sand stockpiles, beaver‑mitigation work with FWP, and a pavement‑markings contract expected in October; the board approved a 2.5% COLA addendum for Robert Pesha & Associates and released collateral for Shadowwood Storage Units Phase 1.
Get email alerts on the Roads And Contracts topic
No spam. Unsubscribe anytime.
Dave Prunty of the Road Department updated the board on August and seasonal operations and construction matters, and commissioners approved two routine contract and bond items.
Prunty said a recent software and hardware upgrade at the asphalt plant produced a mix that met design parameters on the first test—he reported an oil content of 5.63% against a target of about 5.65%—and described crusher and aggregate work that prepared road base for overlay projects. He said salt‑sand piles and satellite shop stockpiles are in place for winter and that crews have been addressing beaver issues near Ashley Lake; the department is working with Fish, Wildlife & Parks and a beaver specialist on a fencing solution and will handle materials and permitting as required.
Prunty noted the pavement‑markings contract was awarded to Solo Markings of Billings; he said Solo's schedule is full until early October but the contract calls for completion by Oct. 15 and the crew expects about three days of on‑site work.
On reclamation, Prunty reported contractor LHC has begun hauling topsoil to the Sheepherder pit and will seed after Oct. 1 under county seeding rules; DEQ Phase 1 release will be filed after seeding, with a Phase 2 release following monitoring over two seasons if growth meets standards.
Commissioners approved an addendum to the Robert Pesha & Associates land surveyor professional services agreement to apply a COLA equal to the county employee COLA (2.5%). They also approved release of collateral associated with Shadowwood Storage Units Phase 1 (bond history noted in the staff report as GM234177 and GM234184 after a transfer of ownership and an amended subdivision improvement agreement with anticipated completion date Dec. 1, 2025).
What's next: Road staff will finalize contracts, monitor pavement‑marking schedules, continue beaver‑mitigation coordination with FWP, and complete reclamation steps tied to DEQ releases; administrative staff will process the contract addendum and bond release paperwork.