Successor agency approves amended funding and contracts to replace Lake Elsinore Diamond Stadium field
Summary
The successor agency approved amended agreements and funding through the ROPS real property tax trust fund to replace the Diamond Stadium playing field after an MLB audit. Staff reported quotes rose—field services from $128,770 to $154,010—and recommended a 10% contingency; the successor agency approved consent items 17–23 unanimously.
Get email alerts on the Stadium Field Replacement topic
No spam. Unsubscribe anytime.
The successor agency of the City of Lake Elsinore approved revised agreements and funding to replace the playing field at Lake Elsinore Diamond Stadium after a routine Major League Baseball audit identified a minor grade noncompliance.
City Attorney Leibold told the board the department of finance has approved allocation of Real Property Tax Trust Fund monies through the ROPS (Recognized Obligation Payment Schedule) process and that the agency had received the formal approval letter the same day. "We've received the formal letter approving those funds today. So quite timely that we have this on the agenda," Leibold said.
Leibold reported the two vendor quotes for the field replacement increased and provided figures to the board: field‑services work rose from $128,770 to $154,010. He recommended the board approve both agreements with the modified proposals and a 10% contingency on the modified amounts; he said the total project remains within the ROPS‑allocated funding.
The successor agency moved items 17–23 as a block; Agency Member Johnson made the motion and Agency Member Sheridan seconded. The motion passed unanimously with all members present voting in the affirmative.
The action places the contract amendments and contingency authorization on record and clears the funding pathway for the field replacement; staff said the project remains within the ROPS allocation approved by the Department of Finance and will proceed per the agreements presented.
What happens next: staff will finalize the amended agreements and proceed with procurement and scheduling for the field replacement work, including the 10% contingency Leibold recommended. The successor agency did not provide a specific start date at the meeting.