Collierville approves TDOT utility-relocation contract for Wolf River bridge project

Board of Mayor and Aldermen, Town of Collierville · January 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved utility-relocation contract No. 9585 with the Tennessee Department of Transportation to move an 8-inch sanitary force main as part of the Wolf River bridge replacement; TDOT's Chapter 86 program may reimburse up to 100% of eligible costs, capped at $2.5 million.

The Collierville Board of Mayor and Aldermen voted Jan. 12 to approve utility-relocation contract No. 9585 with the Tennessee Department of Transportation for a project associated with replacement of Wolf River bridges.

Public Utilities Director John Fox told the board the town must relocate an 8-inch sanitary sewer force main that conflicts with the new bridge alignment. He said the project "qualifies for TDOT's Chapter 86 utility relocation program, which allows for up to a 100% reimbursement of eligible costs, capped at $2,500,000." Fox provided the town's engineering consultant's opinion of probable costs and explained environmental work and preliminary engineering are complete; TDOT plans to bid construction in December 2026.

Fox also said the total project budget is approximately $1,485,372.40, including a 10% contingency of about $135,000, and that $1,415,553.80 is eligible for reimbursement under TDOT policy; the remaining roughly $69,818.60 would be the town's responsibility for non-reimbursable items in the public right-of-way.

Alderman Jordan moved to approve the contract; the board approved the motion by roll-call vote.

What happens next: with the contract approved, staff will proceed with TDOT coordination and reimbursement paperwork as the project advances toward a 2026 construction bid schedule.

Sources: Presentation by John Fox, Public Utilities Director, Jan. 12, 2026.