Collierville board approves amendment to library design contract to move project into bidding phase

Board of Mayor and Aldermen of Collierville · February 23, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Collierville Board of Mayor and Aldermen unanimously approved Amendment No. 4 to the professional services contract for the Cairo Birch Library expansion, adding $153,700 for additional design and survey work and moving the project toward bidding.

The Collierville Board of Mayor and Aldermen on Feb. 3 unanimously approved Amendment No. 4 to a professional services agreement for the Cairo Birch Library expansion, advancing the project into the bidding phase.

Katrina Amos Atkins, deputy talent administrator, told the board Amendment No. 4 requests an additional $153,700, including $1,400 for additional survey work, to address changes in the expansion size and finalize construction documents. "Amendment number 4 finalizes the project into the bidding phase," Atkins said, and staff recommended approval so the design can proceed to procurement.

Atkins reviewed the contract history: the original agreement, approved in September 2024, was for $743,500; Amendment No. 3 in September 2025 increased the total by $137,900 to about $900,700; Amendment No. 4 was described by staff as bringing the agreement to a fee not to exceed approximately $1,053,000.

A motion to approve the amendment was made and seconded and passed by unanimous roll call. The transcript contains a numeric discrepancy in the motion language recited aloud: the motion text in the record recites a not-to-exceed figure of $1,000,054,400, which sharply conflicts with the earlier staff summary showing a total near $1,053,000. The board approved the amendment after the motion and roll-call vote; staff numbers in the presentation (Amendment No. 4 = $153,700; estimated total ≈ $1,053,000) are reported here in preference to the inconsistent figure spoken during the motion.

The approval moves the library expansion design into the procurement and bidding phase; staff indicated additional work will follow to finalize construction documents and begin solicitation for contractors.