Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Infrastructure topic

No spam. Unsubscribe anytime.

Commissioners approve change orders, jail water-heater replacement and fiber work for county facilities

Floyd County Board of Commissioners · February 3, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Floyd County commissioners approved a $8,320.40 traffic-signal change order (state-funded per the transcript), a $40,593 low bid to replace a jail water heater, and additional electrical and fiber work at the county government center covered by contract contingency and ad-alternate bids.

County officials moved forward on several facilities and infrastructure items during the meeting, approving a traffic-signal change order, a jail water heater replacement and additional work on the county government center.

COO Nick Creeby described a change order of $8,320.40 for the Charleston Road project to replace a signal detector housing and run new wire to an existing traffic signal. "This project, construction is being funded by INDOT, 100% on the construction," Creeby said; later comments in the transcript also referenced NDOT regarding participating activities (the transcript uses both agency labels).

Creeby presented three quotes to replace one of the jail’s two water heaters; Greenwell Plumbing submitted the lowest bid at $40,593 and the commission approved the low bid for replacement. Creeby indicated one unit operates as a backup and that the replacement was not optional.

On the county government center project, Creeby said Kevco Construction requested a $10,536 electrical change to add data and a SmartScreen in the third-floor conference room. He also described a fiber ad-alternate bid of $73,680 to bring fiber under the street from the jail and county complex; the contract’s $95,000 contingency had about $38,867 previously expended, leaving roughly $56,133 to cover additional costs. Commissioners approved the presented work by voice vote.

The commission recorded approvals by voice; the meeting transcript records ayes during each motion. Permitting for the underground fiber work was described as tentatively approved, and staff said further contractor submittals to the city’s port of works were necessary before finalizing the fiber installation.