WFISD updates board on McNeil Elementary conversion: $12M project, May target completion

Wichita Falls Independent School District Board of Trustees · December 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District officials described progress converting McNeil from a middle school to an elementary campus, reported the project came in at about $12 million (below an original $14 million estimate), said $900,000 of new furniture is budgeted, and reaffirmed a May target completion date.

District administrators provided trustees with progress photos and a construction update on the conversion of McNeil to an elementary-style campus, reporting the project is on budget and roughly one-third complete.

"We had originally budgeted $14,000,000 and... it ended up being about $12,000,000," an administrator told the board, explaining that lower-than-expected contractor quotes reduced the projected cost. The presenter said the district will finance the work by allowing a maintenance tax note that is rolling off in February 2026 to be replaced by this project's maintenance tax note and by drawing $2,000,000 from the district's fund balance.

Work described at the meeting included completed abatement; saw-cutting and rough plumbing in several wings; gutted classrooms, cafeterias and common areas; plumbing for new bathrooms; and early framing for a STEAM Center. The presenter also said about $900,000 is allocated for furniture, fixtures and equipment (FF&E), and that some items will be repurposed from other campuses where appropriate.

On schedule: administration said contractors are slightly ahead of schedule, the district has used roughly $50,000 of contingency and retains a quarter-million contingency for the project, and the target completion date is May. "They're actually a little bit ahead of schedule, and we're right on budget," the administrator reported.

The board asked about contractor timing and the funding source; administration reiterated the maintenance tax note and fund-balance plan and described the project as a conversion that requires extensive interior work (for example, restroom reconfiguration to meet elementary needs).

The project update was provided as information; trustees approved other items later in the agenda and did not change the construction plan during the meeting.